穆清-殒身不恤

Software
Test Plan (STP)
Template
Software Test Plan
1. INTRODUCTION
The Introduction
section of the Software Test Plan (STP) provides
an overview of the project
and the product
test strategy, a list of testing deliverables, the
plan for development and
evolution of the STP,
reference material, and agency definitions and
acronyms used in the
STP.
The
Software Test Plan (STP) is designed to prescribe
the scope, approach, resources,
and schedule
of all testing activities. The plan must identify
the items to be tested, the
features to be
tested, the types of testing to be performed, the
personnel responsible for
testing, the
resources and schedule required to complete
testing, and the risks
associated with the
plan.
1.1 Objectives
(Describe, at a
high level, the scope, approach, resources, and
schedule of the
testing activities. Provide a
concise summary of the test plan objectives, the
products to be delivered, major work
activities, major work products, major
milestones, required resources, and master
high-level schedules, budget, and
effort
requirements.)
1.2 Testing Strategy
Testing is the process of analyzing a software
item to detect the differences
between
existing and required conditions and to evaluate
the features of the
software item. (This may
appear as a specific document (such as a Test
Specification), or it may be part of the
organization's standard test approach. For
each level of testing, there should be a test
plan and an appropriate set of
deliverables.
The test strategy should be clearly defined and
the Software Test
Plan acts as the high-level
test plan. Specific testing activities will have
their own
test plan. Refer to section 5 of
this document for a detailed list of specific test
plans.)
Specific test plan components
include:
?
?
?
?
?
?
?
?
?
?
Purpose for this level of
test,
Items to be tested,
Features to be
tested,
Features not to be tested,
Management and technical approach,
Pass
Fail criteria,
Individual roles and
responsibilities,
Milestones,
Schedules,
and
Risk assumptions and constraints.
1
9222018 9:27:27 AM
Software Test Plan
1.3 Scope
(Specify the plans for
producing both scheduled and unscheduled updates
to the
Software Test Plan (change management).
Methods for distribution of updates
shall be
specified along with version control and
configuration management
requirements must be
defined.)
Testing will be performed at several
points in the life cycle as the product is
constructed. Testing is a very 'dependent'
activity. As a result, test planning
is a
continuing activity performed throughout the
system development life
cycle. Test plans must
be developed for each level of product testing.
1.4 Reference Material
(Provide a
complete list of all documents and other sources
referenced in the
Software Test Plan.
Reference to the following documents (when they
exist) is
required for the high-level test
plan:
?
?
?
?
?
?
Project authorization,
Project plan,
Quality assurance plan,
Configuration
management plan,
Organization policies and
procedures, and
Relevant standards.)
1.5 Definitions and Acronyms
(Specify
definitions of all terms and agency acronyms
required to properly
interpret the Software
Test Plan. Reference may be made to the Glossary
of Terms
on the IRMC web page.)
2.
TEST ITEMS
(Specify the test items included in
the plan. Supply references to the following item
documentation:
?
?
?
?
?
?
?
?
9222018
9:27:27 AM
2
Requirements specification,
Design
specification,
Users guide,
Operations
guide,
Installation guide,
Features
(availability, response time),
Defect removal
procedures, and
Verification and validation
plans.)
Software Test Plan
2.1 Program Modules
(Outline testing to be performed by the
developer for each module being built.)
2.2 Job Control Procedures
(Describe
testing to be performed on job control language
(JCL), production
scheduling and control,
calls, and job sequencing.)
2.3 User Procedures
(Describe the
testing to be performed on all user documentation
to ensure that
it is correct, complete, and
comprehensive.)
(Describe the testing procedures to ensure
that the application can be run and
supported
in a production environment (include Help Desk
procedures)).
2.4 Operator Procedures
3. FEATURES TO BE TESTED
(Identify all software features and
combinations of software features to be tested.
Identify the
test design specifications
associated with each feature and each combination
of features.)
4. FEATURES
NOT TO BE TESTED
(Identify all features and
specific combinations of features that will not be
tested along with
the reasons.)
9222018 9:27:27 AM
3
Software Test Plan
5. APPROACH
(Describe the
overall approaches to testing. The approach should
be described in sufficient
detail to permit
identification of the major testing tasks and
estimation of the time required to
do each
task. Identify the types of testing to be
performed along with the methods and criteria
to be used in performing test activities.
Describe the specific methods and procedures for
each type of testing. Define the detailed
criteria for evaluating the test results.)
(For each level of testing there should be a
test plan and the appropriate set of deliverables.
Identify the inputs required for each type of
test. Specify the source of the input. Also,
identify
the outputs from each type of testing
and specify the purpose and format for each test
output.
Specify the minimum degree of
comprehensiveness desired. Identify the techniques
that will
be used to judge the
comprehensiveness of the testing effort. Specify
any additional
completion criteria (e.g.,
error frequency). The techniques to be used to
trace requirements
should also be specified.)
5.1 Component Testing
(Testing
conducted to verify the implementation of the
design for one software
element (e.g., unit,
module) or a collection of software elements.
Sometimes called
unit testing. The purpose of
component testing is to ensure that the program
logic
is complete and correct and ensuring
that the component works as designed.)
5.2 Integration Testing
(Testing
conducted in which software elements, hardware
elements, or both are
combined and tested
until the entire system has been integrated. The
purpose of
integration testing is to ensure
that design objectives are met and ensures that
the
software, as a complete entity, complies
with operational requirements.
Integration
testing is also called System Testing.)
5.3 Conversion Testing
(Testing
to ensure that all data elements and historical
data is converted from an
old system format to
the new system format.)
5.4 Job Stream Testing
(Testing to ensure
that the application operates in the production
environment.)
9222018 9:27:27 AM
4
Software Test Plan
5.5 Interface Testing
(Testing done to ensure that the application
operates efficiently and effectively
outside
the application boundary with all interface
systems.)
5.6 Security
Testing
(Testing done to ensure that the
application systems control and auditability
features of the application are functional.)
5.7 Recovery Testing
(Testing
done to ensure that application restart and backup
and recovery facilities
operate as designed.)
5.8 Performance Testing
(Testing done to ensure that that the
application performs to customer
expectations
(response time, availability, portability, and
scalability)).
5.9 Regression
Testing
(Testing done to ensure that that
applied changes to the application have not
adversely affected previously tested
functionality.)
5.10 Acceptance Testing
(Testing conducted to determine whether or not
a system satisfies the acceptance
criteria and
to enable the customer to determine whether or not
to accept the
system. Acceptance testing
ensures that customer requirements' objectives are
met
and that all components are correctly
included in a customer package.)
5.11
Beta Testing
(Testing, done by the customer,
using a pre-release version of the product to
verify and validate that the system meets
business functional requirements. The
purpose
of beta testing is to detect application faults,
failures, and defects.)
9222018 9:27:27 AM
5
Software Test Plan
6. PASS FAIL CRITERIA
(Specify the criteria to be used to determine
whether each item has passed or failed
testing.)
6.1 Suspension Criteria
(Specify the criteria used to suspend all or a
portion of the testing activity on test
items
associated with the plan.)
6.2 Resumption Criteria
(Specify the
conditions that need to be met to resume testing
activities after
suspension. Specify the test
items that must be repeated when testing is
resumed.)
6.3 Approval Criteria
(Specify the conditions that need to be met to
approve test results. Define the
formal
testing approval process.)
7. TESTING PROCESS
(Identify the methods
and criteria used in performing test activities.
Define the specific
methods and procedures for
each type of test. Define the detailed criteria
for evaluating
test results.)
7.1
Test Deliverables
(Identify the deliverable
documents from the test process. Test input and
output
data should be identified as
deliverables. Testing report logs, test incident
reports,
test summary reports, and metrics'
reports must be considered testing
deliverables.)
7.2
Testing Tasks
(Identify the set of tasks
necessary to prepare for and perform testing
activities.
Identify all intertask
dependencies and any specific skills required.)
7.3 Responsibilities
(Identify the groups
responsible for managing, designing, preparing,
executing,
witnessing, checking, and resolving
test activities. These groups may include the
developers, testers, operations staff,
technical support staff, data administration
9222018 9:27:27 AM
6
Software Test Plan
staff, and the user staff.)
7.4 Resources
(Identify the resources
allocated for the performance of testing tasks.
Identify the
organizational elements or
individuals responsible for performing testing
activities. Assign specific responsibilities.
Specify resources by category. If
automated
tools are to be used in testing, specify the
source of the tools,
availability, and the
usage requirements.)
7.5 Schedule
(Identify the high level schedule for each
testing task. Establish specific
milestones
for initiating and completing each type of test
activity, for the
development of a
comprehensive plan, for the receipt of each test
input, and for
the delivery of test output.
Estimate the time required to do each test
activity.)
(When planning and scheduling
testing activities, it must be recognized that the
testing process is iterative based on the
testing task dependencies.)
8.
ENVIRONMENTAL REQUIREMENTS
(Specify both the
necessary and desired properties of the test
environment including the
physical
characteristics, communications, mode of usage,
and testing supplies. Also provide
the levels
of security required to perform test activities.
Identify special test tools needed and
other
testing needs (space, machine time, and stationary
supplies. Identify the source of all
needs
that is not currently available to the test
group.)
8.1 Hardware
(Identify
the computer hardware and network requirements
needed to complete
test activities.)
8.2 Software
(Identify the software
requirements needed to complete testing
activities.)
8.3 Security
(Identify the
testing environment security and asset protection
requirements.)
8.4 Tools
(Identify
the special software tools, techniques, and
methodologies employed in
9222018
9:27:27 AM
7
Software Test Plan
the testing efforts. The purpose
and use of each tool shall be described. Plans for
the acquisition, training, support, and
qualification for each tool or technique.)
8.5 Publications
(Identify the documents
and publications that are required to support
testing
activities.)
8.6 Risks and
Assumptions
(Identify significant constraints
on testing such as test item availability, test
resource availability, and time constraints.
Identify the risks and assumptions
associated
with testing tasks including schedule, resources,
approach and
documentation. Specify a
contingency plan for each risk factor.)
9. CHANGE MANAGEMENT PROCEDURES
(Identify the software test plan change
management process. Define the change initiation,
change review, and change authorization
process.)
10. PLAN APPROVALS
(Identify the plan approvers.
List the name, signature and date of plan
approval.)
9222018
9:27:27 AM
8
negro-thrill
oday-温度英文
走马上任-petrol
48个音标表图片-acca考试
代言人英文-韩国歌曲网
只争朝夕的意思-累的英语
真相只有一个日语怎么说-一个狗一个貂打一成语
也是什么意思-消失殆尽
-
上一篇:看谁是强者,十四大背单词软件、在线背单词评测报告
下一篇:十四大背单词软件评测