REV 2 (22.9.2012)

SAFETY INSPECTION CHECKLIST
-Reference No.: EXW-P006
Work Element in Progress:
RFIT Number: SI-
Any items that have been found deficient must be corrected by the Contractor, where applicable, before work or use commences.
This checklist includes, but is not limited to the following:

Safe Access and Workspace
Is there safe access and adequate space for movement available for emergencies, work areas, walkways and
passageways, with adequate lighting / visibility?
Working at Heights / Scaffolds / Platforms.
Are ladders, stairways, and elevated platforms properly located and functioning?
Do Scaffolds and work platforms have a valid inspection tag at access point?
Are floor and man-hole openings etc. properly protected?
Are scaffolds robust, crossed braced, with ladder access to the work platform,?
Are guard- rails and mid- rails provided, and fully boarded with Toe boards fitted?
Falling Objects
Is overhead protection provided for all areas of exposure?
Are spoil materials and construction materials safely stored away from edges of excavations and scaffolds?
Have unnecessary tools, equipment, cleared from the work area?
Are work area housekeeping to a good standard?
Confined Spaces
Is a confined space permit to work operation in place?
Is Gas tester and or attendant present and recording readings?
Is Standby person in position to remove persons from confined space?
YES


















NO






























N/A





























Date: Time:-
Site Locations:
Inspector Name: Photographs Attached: Yes / No
Is equipment in position to allow removal of persons such as harness, retrieval lines, winch, present and

immediately available at work place?
Planning Work for Safety
Has the Contractor coordinated with his Sub-contractors and other operators at site to prevent congestion and
avoid hazards?
Has the Contractor identified utilities and services?
Has Contractor provided temporary flooring, safety nets, scaffolding, barriers, PPE where required?
Are STARRT Cards, safety inspection, work permit, MSDS documents availablebefore work starts?
Electricity
Have all High voltage lines been identified with warning/prohibition signs?
Have all high voltage lines been moved or de-energized, or barriers erected to prevent contact?
Are all distribution boards earthed, power tools triple insulated, and secure?
Are electrical cablings properly tied together, and in good condition?
Are electrical tools and leads in good condition and tagged with date of inspection










-


-


-


-


-


-


-


-